Buckland & Taylor Ltd. Bridge Engineering   ISO 9001:2000 Certified Bridge Engineers  

SECOND ORINOCO RIVER BRIDGE

Second Orinoco Bridge

Location:

Puerta Ordaz, Venezuela

Description:

The Second Orinoco River Bridge comprises a 3.2 km (2 miles) long road-rail crossing carrying four lanes of highway traffic and one rail line. It is 22.4 m (73 ft.) wide.

The South approach comprises 23 spans of 60 m (197 ft.) and the North approach comprises 12 spans of 60 m (197 ft.). These spans were erected by launching from their respective abutments.

The crossing of the main channel of the river comprises two back-to-back cable-stayed bridges, each having a 300 m (984 ft.) mainspan and two 120 m (394 ft.) sidespans with intermediate sidespan piers maintaining the 60 m (197 ft.) module. The cable-stayed spans were mostly erected by the balanced cantilever method.

Owner:

Corporacion de Guayana

Client:

Construtora Norberto Odebrecht, S.A.

Scope of Work:

Buckland & Taylor Ltd. provided review of superstructure construction.


For more information on our bridge engineering services, please Contact Us.